How a Lianto project runs, from sketch to delivery

By Lianto Plastics

A Lianto project has five steps: design, proof, small-scale manufacturing, large-scale manufacturing and delivery. First samples typically arrive 25 to 45 days after the design is confirmed.

[Hero image]

Every Lianto project follows five steps: design, proof, small-scale manufacturing, large-scale manufacturing and delivery. First samples typically arrive 25 to 45 days after you confirm the design, and production starts about 10 days after you approve them. Design and proofing happen in Australia, while tooling and production take place in our partner factory.

What happens during the design stage of a Lianto moulding project?

During the design stage, we turn your starting files or concept into production drawings and review the part for manufacturability in Australia. A project can begin with a finished CAD file, a drawing, a photo of an existing part or only an idea. We accept STEP, IGES, STL and X_T files, PDF and DWG drawings, and sketches, and we sign an NDA first if you ask. Where there is no model yet, we draw one from your sketch. Where you have an existing part without drawings, we reverse engineer it into 3D and 2D drawings.

An engineer then checks whether wall thickness is even, whether there is enough draft for the part to release cleanly, where the gate will sit and how the part will be ejected. Good design for moulding helps minimise flash, sink marks and moulded-in stress. Running this review in Australia before a tool exists is cheaper than modifying a mould after steel is cut.

Why does Lianto 3D print a concept proof before cutting a mould?

Lianto 3D prints a concept proof in Australia so you can hold the part, fit it to neighbouring components and show it to the people who will buy it before committing to tooling. Changes at this point cost only a file edit and a print. Removing steel from a mould is easier than adding steel back, so we settle changes before tooling starts. We explain the reasoning behind proofing first in our guide to 3D printed prototypes.

Some projects end at the proof stage, because a single part or a handful of units does not warrant a production mould. Others use the physical proof to settle the design, and the same CAD file moves on to tooling.

How does a Lianto project move from small-scale runs to large-scale manufacturing?

Small-scale manufacturing covers short runs and precision work to check a product before tooling and high-volume plastic or silicone production begin at our partner factory. Large-scale tooling runs in a set order: tool design, steel machining, finishing, a first trial and adjustment. Those first trial parts are called T1 samples, and our article on T1 samples explains what is measured on them. Standard production runs start at around 3,000 pieces per part, and larger parts can go lower.

You own the mould outright. We store and maintain it free of charge for up to 3 years, and we ship it to you on request. Small tool adjustments after the first samples are carried out at no charge.

How long does a Lianto moulding project take from confirmed design to production?

From a confirmed design to the start of production typically takes roughly 35 to 55 days, before freight. First samples usually arrive 25 to 45 days after the design is confirmed, together with a measurement report and photos for your review. Production then starts about 10 days after you approve those samples, and freight follows once the run finishes.

These are typical timings, and every quotation includes the full schedule for your part. Four factors shift timelines most: late design changes, complex geometry, high-gloss or textured finishes and repeated adjustment rounds. A confirmed design and a chosen material shorten the schedule. Our article on mould tooling time breaks down each stage, including steel machining and polishing.

Who is responsible for each stage of a Lianto moulding project?

Lianto handles engineering, quoting, proofing, project management and customer care, while our partner factory handles tooling and production. You deal only with Lianto, so any question about a drawing, a sample or a delivery date goes to one point of contact.

You also hold key sign-off decisions at each stage. At design, you confirm the file, because the clock for first samples starts from a confirmed design. At proof, you test the print and tell us what to change. At sampling, you review the trial parts and either approve them or send them back with corrections. That approval sets the benchmark for every later run. Prompt decisions keep a project moving, and our work page follows the same path for a collectible figurine shaker.

How are moulded parts inspected before Lianto ships them to you?

Our partner factory runs an ISO 9001 quality system, with RoHS and REACH reports available and parts inspected every two hours during production. First samples come with a measurement report and photos so you can check dimensions against the drawing. We keep a sealed approved sample to verify every production run against, and you are welcome to send your own inspector.

Once production passes inspection, we manage freight to your door anywhere in the world, with a certificate of origin. Dealing with Lianto as one company from engineering review through to delivery is the basis of our how it works page.

Send a drawing, file or idea through the quote form, or call us on 1300 214 070. We will come back with an engineering review and a fixed quotation that includes the timeline for your part.