How long does injection mould tooling take?
At Lianto, first samples typically arrive 25 to 45 days after the design is confirmed, and production starts about 10 days after sample approval. These are typical timings, not a promise: part complexity, finish, steel choice and the number of adjustments all move the schedule.
First samples from Lianto Plastics typically arrive 25 to 45 days after the design is confirmed, and production starts about 10 days after sample approval. These are typical timings, not a promise, and a quotation after the engineering review states the schedule for your specific part. Design, engineering and 3D printed proofs happen in Australia, and production happens in our partner factory.
What are the stages of making an injection mould?
Making an injection mould follows seven stages in sequence, and the total lead time is the sum of each step. At Lianto, a project moves through the following order:
- Design review. The part is checked for moulding problems before any tool is designed, because good part design helps minimise flash, sink marks and moulded-in stress.
- Tool design. The mould layout is drawn, including how the part fills, cools and ejects.
- Steel machining. The cavity and core are cut. Die-sinking EDM, a spark erosion process, is widely used to machine moulds with high accuracy.
- Texturing and finishing. Surfaces are ground, polished or textured. Grinding forms the basis for a rapid and successful polish, and these finishing steps can be time consuming and costly.
- T1 sampling. The first parts are moulded and measured.
- Adjustment. The tool is corrected where samples show a problem, such as spotting the mould to ensure the fit and vent depths are right.
- Approval. You sign off the samples, and production is scheduled.
What affects injection mould tooling lead time?
Steel choice, surface finish, part complexity, late design changes, adjustment rounds and upfront preparation all shorten or extend an injection mould schedule.
Steel is matched to the expected production run and the plastic being moulded. Prehardened steel such as modified P20 offers good machinability and polishability, while through-hardened steels are mostly used for long production runs, abrasive plastic compounds and high pressures. Lianto quotes P20, H13 or S136 steel, with mould life of 100,000 to 500,000 shots depending on the grade.
Surface finish and part geometry change machining and bench time directly. A plain finish is quicker, while a high-gloss polish or a textured surface adds finishing work. Extra features, undercuts and cooling detail also mean more cutting and more dimensions to check at T1 sampling.
Late changes and adjustment rounds add the most delay. Removing metal from a mould cavity is relatively easy, while adding metal can be difficult or impossible without remaking the mould. A change that makes a cavity larger is simple, and one that makes it smaller is not. Each correction also repeats part of the sampling cycle. We adjust small changes after first samples at no charge, though fewer revisions still keep the schedule shorter.
Clear preparation before machining avoids rework. Starting with a confirmed design, settled wall thickness, chosen material grade and clear finish specification lets the engineering review move straight into tool design instead of stalling before any steel is cut.
Why do 3D printed prototypes save injection mould tooling time?
Proofing with 3D printed prototypes saves tooling time by catching fit, shape and assembly problems while the design can still change freely, before steel is cut. Errors found after machining cost the most time because steel is easier to take away than to put back. 3D printing is a practical way to prototype and debug a design before committing to the final tool. Printed parts do not replace moulded ones because material properties and surface finish differ, yet they let physical fit and shape issues surface before the steel stage.
What does Lianto include with an injection mould?
Lianto handles the design review, tool design and 3D printed proofs in Australia, and you own the finished mould. We store and maintain your mould free for up to 3 years and ship it on request, with standard production runs starting at around 3,000 pieces per part. You can read more about our mould making and tooling process before getting started.
To get an engineering review and fixed quotation with a schedule for your part, call 1300 214 070 or send a drawing through our quote page.
Questions
How long until I receive first samples?
Lianto's first samples typically arrive 25 to 45 days after the design is confirmed. This is a typical range, not a promise, and it depends on the part and the finish.
How long after sample approval does production start?
At Lianto, production starts about 10 days after sample approval. Standard production runs start at around 3,000 pieces per part.
What slows tooling down the most?
Late design changes, complex geometry, high-gloss or textured finishes and repeated adjustment rounds are the usual causes. Settling the design and material before steel is cut avoids most of them.
Why make 3D printed prototypes before the mould?
A printed proof shows fit and shape problems while changes are still cheap. Steel is easy to remove from a mould but hard to add back, so finding problems before machining saves time.
Sources
Wall thickness, Envalior
Processing and mold design guidelines, Eastman
Injection molding troubleshooting guide for Eastman copolyesters, Eastman
Uddeholm steel for moulds, tooling applications for plastic moulding, Uddeholm
Polishing of Uddeholm mould steel, Uddeholm
Increasing the Injection Moulding Productivity through EDM Surface Modulation, Procedia CIRP (Elsevier)
Mold inserts for injection molding prototype applications fabricated via material extrusion additive manufacturing, Additive Manufacturing Letters (Elsevier)