What is a T1 sample?
A T1 sample is one of the first parts made from a new injection mould, produced in the first trial. It is measured and inspected against the drawing, and any fixes are made to the mould or settings before a second trial, T2, and approval for production.
A T1 sample is one of the first parts produced from a new injection mould during its first trial. Moulders number trials in sequence, so T1 is the first trial, T2 is the second, and later runs continue from there. Before production starts, real parts from the new tool are inspected against the drawing and either approved or sent back for correction. Because the numbering is a working convention rather than a published standard, confirm what each label means in the moulder's process before placing an order. The purpose of a trial decides how much material and time is needed; to obtain 5 good parts for testing from an untried mould, running 200 shots is typical.
What is checked on a T1 sample?
A T1 sample is checked for cavity fill and moulding defects first, then for dimensions, surface appearance and fit. Early shots show whether the cavity fills, whether the part releases cleanly from the mould and whether faults appear. Common defects include sink marks, jetting and ejector markings, each traced to causes in the part, the mould or the process, along with short shots and flash.
Once the mould produces complete parts, dimensional inspection starts. Formal first article procedures commonly require dimensional results on 10 parts recorded against a ballooned drawing, with a separate set measured from each cavity of a multi-cavity tool. Where colour, grain or surface matter, an appearance approval report is also completed.
What happens in T2 and later mould trials?
T2 is the next trial, run after corrections are made, to confirm that the fixes worked. Adjustments can be made to the mould itself, such as moving or changing the gate to resolve defects, or to process settings such as injection speed and holding pressure. Further trials follow until the parts meet the drawing.
Because manufacturers usually have limited time for mould trials, using a structured procedure to collect data during a trial, define a stable moulding process and document it consistently helps establish reliable settings. Keeping a complete record of operating conditions, pre-trial preparations and changes made during each trial allows the settings that produced approved parts to be reproduced in production.
How does T1 sample approval work?
Approval happens when the buyer reviews the samples and measurement results and accepts them as the standard for production. In formal manufacturing, the production part approval process lets a moulder demonstrate that it understands the processes needed to produce consistent quality at production rates.
Approval rests on three items: parts that meet the drawing, a measurement report confirming they do, and a retained master sample that sets the reference for later runs. For a multi-cavity tool, one master sample is typically retained from each cavity unless the buyer specifies otherwise. If a sample fails inspection, the mould or process is corrected and another trial is run before production begins.
What should you ask for before a T1 mould trial?
Before tooling begins, agree in writing on how trials are defined, what inspection records will be supplied and how approved samples will be kept. Settling these points before the mould is made avoids disputes at the sample stage. Your agreement should cover:
- A definition of T1 and T2 as the moulder uses them.
- The measurement report and photos for each trial.
- Which dimensions are measured, and from which cavities.
- What was changed between trials, and why.
- A retained approved sample for later comparison.
How does Lianto Plastics handle T1 samples?
At Lianto Plastics, first samples typically arrive 25 to 45 days after the design is confirmed, with a measurement report and photos. Small changes after the first samples are adjusted at no charge, a sealed approved sample is kept as a reference, and production starts about 10 days after sample approval. Design, engineering and 3D printed proofs are done in Australia.
To see each stage from tooling through to production, read how the process works. For an engineering review and fixed quotation, call 1300 214 070 or send your drawing through our quote form.
Questions
What is a T1 sample?
It is a first sample from a new mould, taken from the first trial. It lets the buyer and the moulder see real parts, measure them against the drawing and decide what needs adjusting.
What is checked on a T1 sample?
Fill and defects such as short shots, flash, sink marks and warping, then dimensions against the drawing, surface appearance and fit. The results are recorded in a measurement report.
What happens after T1?
Corrections are made to the mould or the process, and a further trial, often called T2, confirms they worked. Trials continue until the parts meet the drawing and the buyer approves a sample.
How long does it take to get first samples at Lianto?
First samples typically arrive 25 to 45 days after the design is confirmed, with a measurement report and photos. Production starts about 10 days after sample approval.
Sources
Processing and mold design guidelines, Eastman Chemical Company
Development of a Mold Trial Procedure for Establishing a Robust Process, Western Michigan University
Production Part Approval Process manual (SQM03 Rev B), JELD-WEN
Production Part Approval Process (PPAP), AIAG
Injection-Molding Problems in Engineering Thermoplastics: Causes and Solutions, BASF
2.008 Design and Manufacturing II, lecture 3: injection molding, MIT OpenCourseWare